User guide

Schedule

Schedule shows project tasks as a Gantt chart up to 60 weeks, complete with phases, status, progress, exact dates, dependencies, baseline, milestones, critical path, and evidence. A date change can shift follow-on tasks, so every edit must be checked before you save.

± 26 minAdmin webProject manager · Planner · Supervisor · Operations manager
Short answer for clients

Vasco's Gantt combines plan and execution. The project date is the starting point, tasks can use relative weeks or exact dates, dependencies show the order, the baseline freezes the comparison plan, and progress shows what's been achieved—but progress does not change automatically just because a daily report is linked.

00

Before you start

Have this ready

  • Choose the right project and make sure the project start date is valid.
  • Break the work into measurable tasks.
  • Set the dependency order without creating loops.
  • Agree on who may replace the baseline and delete tasks/milestones.

Done when

  • All tasks have a phase, time range, status, and sensible progress.
  • Dependencies don't form a cycle and the critical path is readable.
  • The baseline is saved only after the plan is approved.
  • Milestones, exports, and the print view reflect the filters you want.
01

Understand the Schedule components

ComponentHow to read itKey notes
Start week & durationWeek 0 is shown as the first week; duration is 1–60 weeksExact dates can override the relative position
PhasePreparation, Structure, Architecture, MEP, or HandoverPhases help with filtering; they don't create dependencies automatically
Status & progressNot started, In progress, Done, Blocked; progress 0–100%Status can follow progress or be chosen when editing
DependenciesPredecessor tasks that must be taken into accountCycles are rejected; chosen only when editing a task
BaselineA copy of the date/progress plan at the time it's savedThe previous baseline is overwritten; version history is not kept
Critical pathThe longest chain of dependenciesNot a guarantee that every field risk is included
MilestoneA marker for an important result with a date and done statusNot the same as a task and doesn't store a duration

Baseline overwrites the old comparison

Save a baseline only at a clear approval point. The confirmation offers no undo or history of the previous baseline; a new comparison can only be made by saving the baseline again.

02

Build and maintain the project schedule

  1. 1

    Choose a project

    Search and choose a project, then check the start date that anchors the weeks.

    Result: The Gantt shows that project's tasks and milestones.
    To cancel / undo: Switch projects or clear the filter; no data changes.
    If something goes wrong: If the project doesn't appear, check the project's status/access and the spelling of your search.
  2. 2

    Add a task

    Enter the required name, phase, priority/status, start week 0–59, duration 1–60, progress 0–100, or exact start-end dates if needed.

    Result: The task appears in the list and as a Gantt bar.
    To cancel / undo: Choose Cancel before Save. If it's already saved, use Edit, or delete it only if it's truly not needed.
  3. 3

    Add dependencies

    Edit the task, then choose one or more predecessors. Make sure the work order is real and avoid circular links.

    Result: The critical path and task order take dependencies into account.
    To cancel / undo: Clear the dependency selection before Save, or edit again to remove the dependency after it's saved.
  4. 4

    Shift dates deliberately

    When changing start and end dates, turn on Automatically shift follow-on tasks only if all successors really should shift too.

    Result: The task's dates change and, if chosen, successors are adjusted.
    To cancel / undo: Cancel the dialog before Save. After it's saved, edit the dates again; there is no single button to roll back the whole chain.
  5. 5

    Update progress

    Drag the progress control or edit the number after verifying in the field. Status will reflect the progress according to the screen's rules.

    Result: The Gantt and statistics use the latest progress.
    To cancel / undo: If saving fails, the slider returns to the old value. If a wrong value was saved successfully, set it to the correct number again.
  6. 6

    Link reports and photos

    Choose the related daily report as provenance and upload one photo/evidence if needed. Uploading a new photo replaces the previous draft photo.

    Result: The task can be traced back to the related report and evidence.
    To cancel / undo: Use the X button to clear the photo from the draft. A file already uploaded to storage can remain even if the form is canceled; don't rely on Cancel to delete the physical file.
  7. 7

    Add a milestone

    Enter the required name and an optional due date, then Save. Mark it done only after the result has actually been achieved.

    Result: The milestone appears on the timeline and its done status can be toggled.
    To cancel / undo: Cancel before Save. The toggle reverts if the server fails; if a wrong one succeeds, toggle it again.
  8. 8

    Save the baseline

    After the plan is approved, choose Save baseline and read the confirmation that the old comparison will be overwritten.

    Result: The current dates and progress become the variance comparison.
    To cancel / undo: Cancel at the confirmation. Once saved there is no undo; a new baseline can replace a wrong one.
  9. 9

    Filter, export, or print

    Use phase, status including late, and search, then export CSV or open the print view.

    Result: The CSV uses the tasks from the active filter; print opens in a new tab.
    To cancel / undo: Clear the filters to go back to all tasks. Closing the print tab doesn't change the schedule.
03

Task and milestone statuses

StatusUse whenHow to reverse
Not startedThe work hasn't begunRaise the progress or edit the status
In progressProgress between start and finishChange progress/status after verification
CompletedThe result has been acceptedLower the progress or change the status if it's wrong
BlockedAn obstacle is stopping the taskResolve the obstacle, then change the status
LateThe deadline has passed and the task isn't doneUpdate the actuals/deadline with a reason; don't just hide the filter
Milestone doneThe result marker has been achievedToggle again if it's wrong
04

Undo, correct, or delete safely

SituationThe right actionWhat still happens
Task/milestone form is openChoose CancelNo new row
Wrong date and cascade not yet savedTurn off Shift follow-on tasks or CancelSuccessors stay on their old dates
Wrong date after the cascadeEdit every affected date againThere is no batch rollback
Wrong baselineSave a new baseline after the plan is correctedThe old baseline can't be restored
Task or milestone deletedNo undo availableDeletion is permanent; re-create only from valid evidence

Don't invent an undo

If the screen doesn't offer an undo, edit, or delete button after a transaction is saved, this documentation does not assume the action can be reversed. Note the reference, stop any follow-up actions, then ask for a correction through the main admin or Vasco support.

05

Troubleshooting

SymptomPossible causesWhat to do
Gantt bar is in the wrong weekThe exact date or the project start date differs from what you assumedCheck the project dates and the task start/end dates
Dependency can't be savedIt forms a cycle or picks an invalid taskRemove the circular link and rearrange the order
Progress reverts on its ownThe inline save failedCheck your connection, reload, then save once
Odd critical pathDependencies are incomplete or durations are unrealisticCheck each task's predecessors and duration
Photo disappeared from the draftThe file was replaced/cleared or the signed URL expiredChoose the file again and save; reload for a new URL
?

Questions and answers

What is the difference between relative weeks and exact dates?

Relative weeks are counted from the project start date. Exact dates set explicit calendar limits and are used for task position when available.

Does a daily report automatically change progress?

No. The report link is a source of evidence; progress still has to be updated by an authorized person.

Can an old baseline be restored?

Not from the current screen. Saving a baseline overwrites the old comparison.

What happens if a task is deleted?

Deletion is permanent and has no undo. Check dependencies, reports, and evidence before you confirm.

Why doesn't the CSV contain all tasks?

The export follows the active filter and search. Clear the filters to export all of the project's tasks.